May 28, 2003
| Work continues even on sunny days. On the three upper levels, floor tiles are being cleaned, stripped and waxed. |
 |
 |
Level One The basement level has been sealed off. The removal of floor tiles and accompanying asbestos abatement work has begun. |
 |
 |
| The floor has been contained and the air is being vented outside. |
 |
 |
 |
 |
| The staff is not allowed into this area while the abatement is proceeding, but we can hear the sounds of work being done, and assume it might look a little like this. |
| Photos by David Haberman. |
|